Here’s an update from one of our Construction Supervisors, Kim Lacorte (who rocks, btw…just thought you all should know):

Last week we accomplished a lot.  Focusing on insulation, we were able to spray foam, install cellulose, and install fiberglass batts.  The best remedy: a cold shower.  Are you itchy?

This week we’ll be focusing on painting Building C’s exterior, completing insulation, and if we pass the insulation inspection, start drywall.  